Proposed Plan of Correction: Unacceptable Response
|
The facility proposes the following PoC.
|
Note: The third column will be filled out for you on the next slide. Try and determine why this PoC is unacceptable before continuing to the answers. |
Required PoC Element |
Facility's Response |
Unacceptable Response |
First element, " PoC must contain the plan of correcting the specific deficiency. The plan should address the processes that led to the deficiency cited." |
A facility representative will assess Individual #1 at the day habilitation center, and his interdisciplinary team (IDT) will meet to review and discuss the findings of the assessment. |
|
Second element, "PoC must contain the procedure for implementing the acceptable PoC for the specific deficiency cited." |
At Individual #1's annual planning conference, the day habilitation center assessments, staff observations, and review of client performance will be discussed. |
|
Third element, " PoC must contain the monitoring procedure to ensure that the PoC is effective and that specific deficiency cited remains corrected and/or in compliance with the regulatory requirements." |
The administrator will ensure proper monitoring.
|
|
Fourth element, "PoC must contain the title of the person responsible for implementing the acceptable PoC." |
Sarah will handle the implementation.
|
|
Did you identify what makes this PoC unacceptable?
|
Go to the next slide for the answers. |