Criterion #5

paste from wordThe fifth criterion of an acceptable PoC is:

When corrective action will be completed.  Must be at least one day past the date of exit.

For example, it may take a week to arrange pest control for an issue, or a month to train all staff on infection control. Therefore, each citation may have its own date of completion, which may differ from the dates for other citations.

Please include the date when the corrective actions will be completed. The completion date must be reasonable for the deficient practice cited but at least one day past the day of exit.